INSTALLATION
Selection of the pool site will determine how much grading
will have to be accomplished prior to the actual dig for the
pool. A level area is best because it will require the
least amount of preparation for the dig, but in many cases
there is no level area, therefore, the site must be prepared to
accept the pool prior to dig. The pool site should be elevated
slightly higher than the surrounding area. It is most
important that drainage from the surrounding area
does not run into the pool.
When dealing with slopes, the severity of the slope will
determine if retaining walls must be built in order to have a
level area for the pool. If the slope is relatively minor, a
simple wall built from railroad ties or landscaping timbers
may be all that is needed, but if the slopes are severe you may
be forced to construct a major load bearing retaining wall.
An ideal excavation is one that
is as close as possible to the dimensions of the pool shell,
but with the following rules in mind. The excavation should
be 2" to 4" deeper than the actual pool for your sand bed. The
sand bed is to level the pool shell and provide a perfect
support base with no voids when the pool is lowered into the
hole. Your excavation should be approximately one foot
longer and one foot wider than the pool shell. This will allow
for a six inch overdig all the way around the pool once it is in
place. Additional hand excavation will be required to insure
the skimmer when attached to the pool will fit in the
excavation. A transit and story pole, when used properly, will
insure an accurate dig.
Sand must be used to bed the shell into the
excavation and for backfill. You will determine
how much sand is needed to be placed on the bottom of the
excavation of all constant depth pools or those with constant
slopes, by setting a grade stake at all four corners, and one on
each side of the centerline in the bottom of the hole. If you are
installing our deeper models with breaks for deep ends, than
each individual depth change must be noted by stakes outlining
each area . By using the transit and shooting down from your
grade stakes indicating the top of the pool, you will know exactly where on the bottom stakes the
pool should be to maintain an exact level for the pool.
An area approximately 4'-6' long, 2'-3' wide and 12" deep
should be dug out at the middle of the deepest end of the pool.
If the pool is going to have a drain in the bottom it could end
up in this area and the sump hole will need to accommodate
the drain as well. This area is for a dry well sump, which has a
gravel bottom, 2" perforated PVC pipe with an end cap
attached to a 1 1/2" or 2" PVC line that is run under the pool
and up and out of the excavation under the deck. This line can
than be attached to a pump. The remainder of the sump hole ,after the pipe is installed ,should be filled
with1/2" or larger gravel. This will allow for underground water that may accumulate under the pool during
and after the installation to be removed, and is a permanent part of the installation.
With the hole properly prepared, all measurements double
checked, and making certain that there is nothing in the
bottom of the hole except a compacted level bed of sand, and
your sump installed, you are now ready
to set the pool.
A suitable sized crane will be utilized for this job. Although
certain size backhoes and trackhoes are capable to do this job,
a crane is the safest and most suitable piece of equipment to
use. It is designed for this purpose and can easily lift the pool
back out of the hole for corrections in the sand bottom if
necessary. Your pool has four lifting areas under the coping at each
corner of the pool shell. Chains are usually shipped with the
pool to attach lifting straps to be attached to the crane.
Most pools are shipped with spanner bars
bolted across the centerline of the pool shell. These spanner
bars are there to prevent the pool from buckling during the
setting procedure and should not be removed at this time.
Rope lines will now be attached to the pool by the installer to help guide it when lifted by the crane. You will now carefully and slowly lift your pool slightly off the ground or trailer and
double check all chains and straps. They will insure everything is properly rigged before proceeding. It is not
advisable to lift the pool during any type of wind. The pool will act as a giant kite. You will make certain wind is at a minimum. Very slowly lift and move the pool to the excavation. It is
recommended to keep the pool as low to the ground as possible, this will help in handling and lower the
effects of wind movement. Once over the hole, you will line up the shell, make certain no debris
has fallen into the hole and slowly lower the pool into the excavation.
With the shell setting in the hole, it is time for
you to check your level. When you are certain the pool is all
the way in the hole, measurements should now be taken with a
transit. They will set their story pole on the top of the coping at
each corner, staying away from seating areas and steps, and take
your measurement at each corner. All four comer will be within
one half ( l /2") of an inch. Particular attention must be made on
all diving models to insure the break points are setting
where they were planned without voids or binds.
When everything is properly measured your pool will be level. It
is not uncommon for you to have to lift and set the
shell several times prior to getting the pool exactly level. Take whatever time is necessary to insure the pool is
within the one half (1/2") tolerance.
The important thing to remember is that Fiberglass Pools are
flexible, and equal amounts of pressure on each side of
the pools walls must be maintained at all times.
You will start by filling the pool
with one foot ( 1' ) of water. This will securely anchor the pool
into the excavation. They will then recheck their measurements
with a transit. This is because these areas may sag and will
require additional reinforcement.
Never attempt to move any part of the shell or coping
with a machine once it has any water in it. It could crack
the shell and void the warranty. If the shell moves
significantly out of level at any point from here on out it may
be necessary to drain the pool and re-level the shell.
With reinforcement in place and one foot of water in the pool,
we may now proceed with the backfill.
You
will now start adding sand around the pool, no dirt.
Dirt is totally unsuitable for this portion of the backfill
and will void your warranty. The sand must fill all voids as
the backfill. The best way to do this is to wash the sand with
water under and around all areas of the shell. By washing
the sand down and removing it slowly, the water will
wash the sand into the areas required. Too much water is not
good, so common sense should be used for the proper balance.
Areas under steps, seats, and the main drain must he
completely filled in with washed sand and compacted to
prevent settling.
The amounts of sand required for each pool is
different, and the amount will also be effected by how close
your hole is to the dig specs. In general, a 12' wide pool will
take 20-30 tons, 14' wide 30-40 tons and 16' 40 tons +. In any
event, you should order 20 tons to be
delivered to the site initially and this will be a sufficient bed for all San Juan pools and allow some sand for
the backfill.
The water in the pool will be added at a rate equal to the rate of backfill, with the water maintaining a level
one foot higher than the sand backfill throughout the entire fill and backfill procedure It is very important to
keep equal amounts of pressure on the pools walls. Too much water could bow and even break the pool
outwards, and to much sand could bow the walls inward. A bowed wall inward means you have added too much
sand and it must be dug out until the wall is straight and a bowed wall outward means your water is too high
in the pool and the sand must be brought up.
The time this procedure takes is determined by the jobs water pressure. Remember, you cannot fill
the pool any faster than they can backfill it
When your backfill is up approximately one third of the pool, this is the time to remove the spanner bar if
your pool came with one. Removing the spanner bar may cause the pools walls to bow out, but by adding
additional sand without adding additional water will cause the walls to bow back in. A proper balance of sand
backfill and water fill in the pool will keep the walls true throughout the entire installation.
All plumbing should be 1 1/2" PVC schedule 40 pipe or
2" if the pump and filter is over 30' feet from the
equipment. The lines around the pool should not go in
until the sand backfill is up high enough to allow setting
these lines, at the height of the returns and skimmer, on
top of the backfill. This will prevent the lines from
sagging, and possible cracking. After they are run, the
balance of the backfill can continue over these lines. You will have separate lines from the pool to
the equipment for the skimmer, sump line and pool
returns. They may have additional lines if you are planning
a pressure side pool cleaner, spa jets or fountain/waterfall.
Make certain all electrical inspections
on lights, bonding and all other electrical work have been
completed and checked off by the local inspectors prior to
proceeding with your concrete. Run the pool for at least 24 hours before
you pour the concrete to insure there are no leaks.
As previously discussed in this manual, the type of
decking you have selected will have determined the grade of
the pool. If you are going to use cantilevered forms as
recommended, the top of the pools coping will be leveled
with your surrounding grade. If you are pouring a regular
deck up to the pools coping, than the top of the coping
should be 4" above the surrounding area. In either event,
you will dig out an
area around the pool exposing the flange of the coping and
just under it. This is important as concrete should be
packed under and over the flange of the pool, as the
deck is poured. This will lock the pool into the concrete
and provide for a much stronger bond of the pool to the
deck. It will also eliminate cracking of the deck where it
meets the pool.
When you set your outside forms, remember you want any water from rain or splash out to
run off the deck, not into the pool. Plan for a slope of 1/4" per foot away from the pool. If your deck is
going to tie into an existing deck, than some type of drain system should be planned to handle the run off.
Proper drainage planning is very important.
An experience concrete finisher will always be used when pouring pool decks, especially when you are doing a
cantilevered deck, as the forms must be taken off at the proper time to allow finishing of the inside of the
form. Fiberglass pools are different from Vinyl or Concrete in that the pools are full when the concrete is
poured.
Pools Spas Information Form Colors Map Email
Pride Promotions Inc.,
334 East 12th Suite 111, Pittsburgh, PA 15120
Tel:
412-462-2111
Fax: 412-462-2424
Copyright 1996, Pride Promotions, Inc. All rights reserved.
Contact our Webmaster with comments or question
regarding this site